KRI Raja Haji Fisabilillah (391) is the lead ship of to be operated by the Indonesian Navy.

Design

Raja Haji Fisabilillah initially was designed with a length of and a beam of , however during the construction it was redesigned to a length of .

Service history The ship's contract was awarded on 16 April 2020, with the contract worth Rp 1,079,100,000,000. Its construction began with first steel cutting on 26 August 2021 at the then PT Daya Radar Utama (later renamed to PT Noahtu Shipyard) shipyard in Bandar Lampung, Lampung.

The ship's keel was laid on 16 November 2022. The ship experienced delays during its construction, which drew some criticism. Although the ship was planned to be handed over in 2023, the construction progress was only at 35% by March 2023.

The patrol vessel was launched on 18 September 2024, and was officially given the name of Raja Haji Fisabilillah two days later on the 20 September. The ship started sea trials in October 2025.

References