The Gegeen Solar Power Plant () is a photovoltaic power station in Zamyn-Üüd, Dornogovi Province, Mongolia.
History The construction of the power station was completed in 2017. It was then officially opened on 21June2018. In September2018, it was commissioned. It was constructed with a cost of US$26million.
Architecture The power station spans over an area of 40hectares.
Technical specifications The power station has an annual generating capacity of 31,162MWh. It consists of 51,840 PV modules, each with 320W of nameplate capacity. The power station also includes a 11/110kV substation and 6km long 2-circuit 110kV overhead transmission lines.
Human resource The power station employs 20people.
See also List of power stations in Mongolia