Uranium mining in the Elliot Lake area (prior to 1955, more commonly known as the Blind River area) represents one of two major uranium-producing areas in Ontario, and one of seven in Canada.

In the mid-1950s, the influx of people to Elliot Lake seeking uranium was described by engineer A. S. Bayne in a 1977 report as the "greatest uranium prospecting rush in the world".

Mining activities peaked around 1959 and 1960 to respond to US military demand for uranium during the Cold War.

By 1958, Canada had become one of the world's leading producers of uranium and the $274 million of uranium exports that year represented Canada's most significant mineral export. By 1963, the federal government had purchased more than $1.5 billion of uranium from Canadian producers for export. The opening of the mines and the workers they attracted led to the creation of the planned town of Elliot Lake.

US demand slumped in the early 1960s, but the increasing use of nuclear power for electricity-generation, in Canada and abroad, prompted some mines back into action.

Production slowed until the 1990s when it ceased. The Elliot Lake area now has ten decommissioned mines and 102 million tons of uranium tailings. Former miners have been left with a twofold increase in lung cancer development and mortality rates.

Area and nomenclature The 200 square mile area north of Lake Huron that was Canada's largest uranium producing area has been referred to by various names as time passed, specifically Algoma, Blind River and Elliot Lake.

Algoma is the name of a wider district that includes this area. Blind River was initially the nearest human settlement, located 12 miles west of the nearest mine, until Elliot Lake was created, which is close to most of the mines.

The only road access to the town of Elliot Lake is via Ontario Highway 108.

Geology Towards the end of the Wisconsin glaciation period, ice flowed approximately south (predominantly at 190°) across the area know known as Elliot Lake. Geologists believe that as the ice sheet retreated back north, it left a large proglacial lake just north of Elliot Lake, probably as part of the main Lake Algonquin. Today's features were created from sediments that sunk while the area was below the 335m deep lake. As the ice retreated, about 10,800 years ago, the ice holding the lake melted, causing the sand and gravel sediments to spill into the valleys.

Microscopic grains of uranium occur in ores of uraninite, brannerite and monazite amongst pyritic sheets of quartz-pebble rock.

History

Traditional territory

The area is the traditional territory of the Serpent River First Nation and also part of the Huron Robinson Treaty land.

In 2021, the Serpent River nation representatives described community consultation about mining activities as "minor."

19th century Known at the time as the Blind River area, the Elliot Lake area is situated between the Sudbury Nickel mining area and the abandoned Bruce Mines and was subsequently prospected for gold and copper during the 19th century.

Uranium was first discovered in Canada by John Lawrence LeConte in 1847, who named the new mineral coracite. The exact location of his first discovery was unclear, but was understood to be approximately 70 miles north of Sault Ste. Marie on the shore of Lake Superior. A lack of an exact location and the absence of radioactivity detectors resulted in failures of surveyors or prospectors to repeat his find.

Mid 20th century – uranium discovery In 1948, Karl Gunterman, financed by Aime Breton, with a Geiger counter discovered radioactive conglomerate near Lauzon Lake in Long Township, Ontario. Their discovery was investigated by geologist Franc R. Joubin, who in 1952 found a uranium deposit in Spragge.

In 1953, Joubin persuaded Joseph H. Hirshhorn to finance exploratory drilling and Hirshhorn signed a contract with Eldorado Mining and Refining Ltd, the Canadian Crown Corporation that bought all uranium in Canada; together they quickly started the Pronto Mine. News of the mine and the 1,400 stakes claimed by Joubin and Hirshorn resulted in a rush of prospectors to the area who filed 8,000 claims that summer. The uptick in uranium staking was known as the Backdoor Staking Bee. Mapping by W. H. Collins of the Geological Survey of Canada led to the discovery of more uranium around Quirke Lake and Elliot Lake (the lake proper, not the town of the same name). By 1958, Eldorado Mining and Refining Ltd estimated that the area had 320 million tons of uranium ore, with on average 2.38 pounds of uranium oxide per ton.

Throughout the 1950s, the majority of the world's uranium came from Elliot Lake, which became known as the "Uranium Capital of the World".

1957 saw bustling activity as contractors blasted paths through rock to make roads, sinking shafts and building uranium processing mills. According to the University of Waterloo's Earth Sciences Museum, "Never before in the history of Canada has so much money been spent so quickly in one place."

Throughout the 1950s, the people of the Anishinaabek First Nation of the Serpent River were systematically excluded from all decisions about resource extraction in their area.

Late 1950s boom 1958 was the first full year of mining production, and saw a $200 million of uranium sales, making uranium Canada's number one metal export, and Elliot Lake Canada's largest producer.

From 1959 to 1960, Elliot Lake organized town was created and other mines were constructed to meet the growing US demand for uranium.

In November 1959, the US announced its plans to stop stockpiling uranium and to cease procurement after 1962, resulting in the closure of five mines in 1960. However, by 1966 the global demand for uranium for energy purposes prompted increased production in the area, by 1970 the area had produced $1.3 billion of uranium oxide. Mining companies funded the creation of a Nuclear Museum.

The mines all started producing between 1955 and 1958, supplying US military needs.

1960s drop in demand When the United States Atomic Energy Commission declared in 1959 that it would no longer stockpile uranium, and not renew procurement contracts beyond 1963, seven of the remaining nine mines closed. The other two mines, Denison and Nordic, remained open to supply Canadian federal uranium stockpiling needs while Pronto switched activities to supporting the nearby Pater copper mine. At the same time, Rio Algom Limited was created and became the owner of the seven closed mines, plus the Nordic and Pronto mines.

The mine closure resulted in the population of Elliot Lake town dropping from about 24,877 to 6,000 residents, having an immediate negative impact on the local economy.

Rio Algom later became a subsidiary of BHP.

1970s onwards In early 1972, Australia, France, South Africa, and Rio Tinto Zinc formed a cartel to control the supply and pricing of uranium, using price fixing and bid rigging.Stewart, Larry R. “Canada’s Role in the International Uranium Cartel.” International Organization, vol. 35, no. 4, 1981, pp. 657–89, . Accessed 24 Apr. 2022. This continued until the cartel was exposed by Friends of the Earth Australia in 1976.

The growing demand for uranium for nuclear power stations being built in the 1970s promoted Rio Algom to increase production at Quirke Mine and reopen Panel Mine in 1979 and later Stanleigh Mine (1983).

Decommissioning started from 1992 and concluded in 2001 when vegetation was added to Pronto Mine. Today, all mines are now fully decommissioned, meaning that mine openings are closed up, all buildings are removed and the sites have been revegetated.

Ontario Hydro cancelled its contract to buy uranium from Rio Algom in 1990 and from Denison Mines in 1992, although Stanleigh Mine continued production until June 1996.

Currently, Rio Algom owns nine of the mines (Stanleigh, Quirke, Panel, Spanish, American, Milliken, Lacnor, Buckles and Pronto) and Denison Mines owns the others.

As of 1980, Elliot Lake supplied 90% of the uranium used in Ontario.Mining, Milling and Refining of Uranium in Ontario, Final Report, Select Committee on Ontario Hydro Affairs, December 1980, 4th Session, 31st Parliament, 29 Elizabeth II, page 16.

Mining process Mined ore consisted of pyritized quartz conglomerate with 0.1% to 0.2% uranium. The ore was acid leached to extract the uranium using sulphuric acid.

Tailings were neutralized before being deposited, however exposed tailings released acid and radium-226 before barium chloride and lime treatment was started in the 1970s.

Individual mines Buckles Mine

Buckles mine is located on the south of the Quirke Lake syncline, close to the Nordic Mine. In 1955, Spanish American Mines Limited bought the mine from the original owner of the claim, Buckles Algoma Uranium Mines Limited.

The uranium ore was reported to be 486,500 tons, at 0.124% U3O8, located in a ten-feet-thick zone, 75 feet below the surface.

From 1958 onwards ore from the mine was processed at the Spanish American mine, where it was transported and treated at rate of approximately 500 tons per day. The mine closed in 1958 after all the ore had been extracted.

Twelve Mt of ore remains on the shared tailing management area with Nordic Mine under vegetative cover.

Can-Met Mine

Can-Met's location was first staked by Carl Mattaini who sold it to Can-Met Explorations Limited. The 1958 reporting indicated 8,362,069 tons of ore, which included 6,642,380 tons of uranium ore, with a partly proven average uranium grade of 1.832 pounds of uranium oxide per ton, after dilution. The mine is located on the south shore of Quirke Lake, 15 miles from Elliot Lake.

The mine had two shafts to 2,127 and 2,395 feet. There was a processing plant that could process 3,000 tons of ore per day built in October 1957. Tailings were deposited in the natural basin south of the mill.

Denison Mine

Denison Mine (also known as Consolidated Denison Mine) is located 10 miles north of Elliot Lake. It is just south of the Quirke Mine, and just west of the Panel and Can-Met Mines, just north of Spanish American and Stanrock mines. Following successful staking of the Pronto Mine property, mining claims were staked un the summer of 1953 by F. H. Jowsey, A. W. Stollerty and Associates. These stakes were purchased by Consolidated Denison Mines Limited in 1954. Denison undertook geological surveys and diamond drilling.

The mine started in September 1957, and there was mill on site to process 6,000 tons per day. The average production was 2,676 tons per day and the ore milled had an average of 2.63 pounds of uranium oxide per ton. 1957 estimates of ore reserves were of 136,787,400 tons above another zone 100-feet lower.

63 million tons of tailings were deposited in Williams Lake, Bear Cub Lake, and Long Lakes. The mine was decommissioned by Denison Mines in 1997.Ludgate, I R, Counsell, H C, Knapp, R, & Feasby, D G. Decommissioning of denison and Stanrock tailings management areas. Canada.

Lacnor Mine

Lacnor Mine (also known as Lake Nordic Mine) is located on the south limb of the Quirke Lake syncline, four miles from Elliot Lake. It is located just north of Nordic Mine, and just east of Miliken Mine and just south of Stanleigh Mine. It was purchased by Northspan Uranium Mines, a subsidiary of Rio Tinto.

Diamond drilling started in 1954, which found ore. Two shafts were sunk and a processing plant with 3,800 tons per day was constructed. 1957 reports indicated an ore reserve of 8,289,207 tons that produced an average of 0.101% uranium oxide. Tailings were deposited in the valley east of the mill.

The mine closed in 1960 and was decommissioned from 1997 to 2000. 2.7 Mt of tailings remain on site

Miliken Lake Mine