The Zhangzhou Nuclear Power Plant () is a nuclear power station under construction in Lieyu Town, Yunxiao County, Zhangzhou on the coast of Fujian Province, in southeast China. The plant is owned by CNNC Guodian Zhangzhou Energy Co. Ltd., established in November 2011, which is owned by China National Nuclear Corporation (51%) and China Guodian Corporation (49%). CNNC originally planned to have AP1000 light water reactors, but later changed plans to the Hualong One design.

China's Ministry of Ecology and Environment issued construction licenses for Zhangzhou units 1 and 2 on 9 October 2019, and first concrete for Unit 1 was poured one week later, on 16 October.

China's State Council approved the construction of two Hualong One units as Phase II on 14 September 2022. Construction of the first began on 22 February 2024.

The first unit began commercial operation on 1 January 2025, 5.2 years after the start of construction.

The second unit began commercial operation on 1 January 2026.

From May 2024, units 5 and 6 are steadily advancing site selection and preliminary environmental impact assessment work.

Reactor data The Zhangzhou Nuclear Power Plant consists of 6 planned reactors. Unit Type Net Capacity Gross Capacity Construction start Grid connection Commercial operation start Notes Phase I Unit 1 Hualong One 1126 MW 1212 MW 16 Oct 2019 28 Nov 2024 1 Jan 2025 Unit 2 Hualong One 1126 MW 1212 MW 4 Sept 2020 24 Nov 2025 1 Jan 2026 Phase II Unit 3 Hualong One 1129 MW 1214 MW 22 Feb 2024 2029 (est.) Unit 4 Hualong One 1129 MW 1214 MW 27 Sep 2024 Phase III (In Plan) Unit 5 Hualong One 1129 MW 1214 MW Unit 6 Hualong One 1129 MW 1214 MW