The Caltrain Express Program (CTX) was implemented from 2002 to 2004 to establish the Baby Bullet express service, which shortened the transit time on the Caltrain commuter rail line between San Francisco and San Jose, and certain stations in between. New locomotives and rolling stock were purchased for dedicated express service, bypassing most stations; quad-track overtake sections were added in two locations along the Peninsula Corridor right-of-way to allow express trains to pass slower local trains that were making all stops; tracks were also upgraded with continuous-welded rail; a centralized traffic control system was added; and crossovers were added every few miles to allow single-tracking trains around disabled trains. Congresswoman Jackie Speier, then serving as a California State Senator, is credited with securing the funding for CTX and one of the new locomotives acquired for the project is named for her as a result. During commute hours, the Baby Bullet went up to 20 percent faster than driving south from San Francisco to San Jose. On September 21, 2024, with the completion of the Caltrain modernization project and the transition to electrified trains, the Baby Bullet was renamed as simply the Express service.

History In 1997, after plans to extend Caltrain to downtown San Francisco were put on hold, the Peninsula Corridor Joint Powers Board (PCJPB) started the Rapid Rail Study, which was published as a draft in October 1998. The 1998 Rapid Rail Study prioritized planned capital improvements to implement the 1997 Caltrain 20-Year Strategic Plan, which sought to improve service and increase ridership, which was assumed to correspond directly to improved service (through decreased transit times and increased train frequencies). The highest-priority projects were intended to rehabilitate the line to "reverse decades of deferred maintenance" and enhance the line by adding overtake tracks to implement express service. After rehabilitation and enhancement, the Rapid Rail Study called for electrification of the line.

Proposed rehabilitation work included rebuilding tracks and grade crossings to enable Caltrain to raise the systemwide speed limit to and replacing bridges, culverts, and signals. The initial enhancement projects included adding third overtake tracks in Burlingame (between the stations at Millbrae and San Mateo, for northbound trains) and San Mateo (between 9th Avenue and Hillsdale, for southbound trains) to allow express trains to pass slower all-stop local trains, and adding a third turnback track in Palo Alto to allow more frequent short-line service. In 1999, PCJPB published an implementation plan for the Rapid Rail Study which called for a $280 million investment from the three counties served by Caltrain.

California State Senator Jackie Speier and Caltrain leadership are credited with the idea to provide an express service for Caltrain during a brainstorming session. Senator Speier sponsored Senate Bill 2003 in February 2000 authorizing to fund CTX; the first draft of the bill included funding to create "little bullet" express Caltrain service between San Francisco and San Jose (with the goal to cut transit time in half compared to local, all-stop service) and also to rehabilitate the Dumbarton Rail Bridge in preparation to reroute Altamont Corridor Express (then Altamont Commuter Express) service from Stockton over the Dumbarton Rail Corridor. By March 2000, the bill was being referred to as the "Baby Bullet Bill" and it passed the Senate Transportation Committee on a 9–0 vote in April 2000 after it had been amended to remove Dumbarton Rail and focus solely on establishing express service. The funding request for the Caltrain express service was later incorporated directly into the Governor's budget. CTX was one of the projects recommended by the Metropolitan Transportation Commission (MTC) under Resolution 3434 in December 2001.

Construction CTX officially broke ground during a ceremony held at 4th and King on June 28, 2002. The groundbreaking was attended by officials and politicians who had supported CTX, including Senator Speier, Governor Gray Davis, Secretary of Transportation and Housing Maria Contreras-Sweet, MTC Commissioner Sue Lempert, Caltrans Director Jeff Morales, and San Mateo County Supervisor Mike Nevin. At the time, it was the largest capital improvement program for Caltrain.

During CTX construction, Caltrain shut down weekend service for two years starting in July 2002 to allow track work. samTrans introduced the RRX bus line to temporarily replace weekend Caltrain service, but RRX was not a direct replacement, as the ride between San Francisco and San Jose was scheduled for 98 minutes, buses only ran until 8 P.M., and the line only had two intermediate stops, at Hillsdale and Palo Alto. After construction was complete and weekend service resumed in June 2004, Caltrain offered free rides the first two weekends to lure riders back and to thank riders for their patience. During construction, service was also reduced to a single track on Thursday and Friday nights after 9 p.m.

Baby Bullet service By April 2004, Caltrain was showing off the rolling stock it had acquired for Baby Bullet service. Construction was substantially complete by May 2004 when Caltrain began running "test" trains on the weekends to shake down the system and gain crew experience, and the Baby Bullet trains entered revenue service on June 7, 2004; the first northbound Baby Bullet discharged over 600 passengers upon its arrival in San Francisco at 6:45 a.m., and had carried more than 1,000 during its inaugural run. The first southbound Baby Bullet left San Francisco with 420 passengers at 7:20 a.m. Baby Bullet trains often ran at standing room capacity during the first year.

Just prior to the inauguration of Baby Bullet service, Caltrain served an average of 27,000 riders per weekday. One year later, Caltrain ridership had increased by 12%, and by 2014, ten years later, Caltrain ridership had more than doubled to over 60,000 riders per weekday. Notably, once San Mateo County commuters were given the choice between BART and Caltrain to San Francisco after the completion of the BART extension to San Francisco International Airport, many riders continued to prefer Caltrain and the Baby Bullet service, which was cheaper and quicker than switching to BART at Millbrae, in part because Caltrain, which follows the 1907 Bayshore Cutoff route constructed by Southern Pacific, does not take a long detour west around San Bruno Mountain to reach San Francisco.

In addition to having one of the new locomotives named for her, Senator Speier received MTC's John F. Foran Legislative Award for her pivotal role in bringing Baby Bullet service online. CTX received an award from the California Transportation Foundation as the Program of the Year for 2004. During the same ceremony, Speier was honored as the Legislator of the Year.

In 2017, the Rail and the California Economy report noted that Baby Bullet trains operated at 95% on-time performance (making stops within ten minutes of scheduled times) and, at around 60 minutes from San Francisco to San Jose, was faster than driving south on U.S. 101 during key commute hours. Driving times during peak afternoon commute hours could reach 75 minutes or more.

On September 21, 2024, with the completion of the Caltrain electrification project, the Baby Bullet was renamed as simply the "Express" service.

Design

Caltrain split the CTX project into two separate phases, based on geographic region. The North CTX extended from San Francisco to Redwood City, and the South CTX spanned the tracks from Menlo Park to Santa Clara. The North CTX contract was awarded in April 2002 to the joint venture partnership of Herzog Contracting Corporation and Stacy & Witbeck (Herzog-Stacy-Witbeck). Herzog-Stacy-Witbeck also won the South CTX contract, as announced in January 2003. The key elements of CTX were the overtake tracks, high-speed crossovers, and a central traffic control system which collectively allowed a single office to route trains. To support smoother operation at higher sustained speeds, Caltrain also laid down continuous-welded rails.

Station rebuilds During the CTX project, Caltrain rebuilt the Bayshore station, relocating it slightly south of the prior location to accommodate the north quad track overtake section ending just south of Tunnel #4. This moved nearly all of the Bayshore station out of the City and County of San Francisco and broke a planned intermodal connection to the Third Street Light Rail Project, the first expansion phase of the Muni Metro light rail system, which was building tracks down Third Street. The new T Third Street line, which opened in 2007, terminates at Sunnydale Station as Muni Metro has never built any tracks in San Mateo County, and a planned loop extension to Bayshore was studied in 2012. A small rail bridge south of Bayshore was built over a creek as part of CTX.

The Lawrence station was in the right-of-way planned for the south quad-track overtake section, so Lawrence was rebuilt with new platforms and an under-track pedestrian tunnel. Work at Lawrence was anticipated to be completed by the end of 2003, and the rebuilt Lawrence was opened in March 2004.

The Millbrae station also received some upgrades; a third track was added and existing tracks were relocated, requiring Caltrain to demolish the existing platform. Millbrae station updates were scheduled to complete with the opening of the new intermodal station in January 2003.

Track upgrades (overtakes, crossovers, and traffic control)

CTX added quad-track overtake sections near the cities of Brisbane and Sunnyvale. During the initial design phase, overtakes were also announced for Millbrae and Redwood City. Millbrae gained a third track, and Redwood City added two sidings near Redwood Junction, approximately between Chestnut Street and Fifth Avenue. From north to south, the completed quad-track overtake sections are: Brisbane, approximately between Candlestick Cove and Tunnel #4 (overlaps Bayshore Station) Sunnyvale, approximately between Fair Oaks and Bowers (overlaps Lawrence Station)

CTX also included crossover switches, which improved operating flexibility to allow trains to bypass stalled trains, and a centralized traffic control (CTC) system, which allowed track signaling and switching operations to be handled from a single facility in San Jose, rather than relying on dispatched crews throwing manual switches. Prior to CTX, trains typically had to stop and de-board operators and conductors, who would throw switches by hand. Although CTC was already partially implemented near the two main terminals at San Francisco and San Jose, CTX added CTC throughout the route, and 12 signal bridges were added to the line in total.

By November 2002, Caltrain had rebuilt of track as part of the North CTX project, which included conversion to continuous welded rail and replacement of wooden ties with concrete ties. Full-speed testing of track upgrades occurred over two weekends in May 2004, just before the Baby Bullet service started in June. Crews and central control practiced overtaking slower trains and routing around delays induced by disabled trains.

Stops and scheduling