Telangana Super Thermal Power Project (TSTPP) is a power plant under construction in Telangana, India. It has a power capacity of 1600 MW (2×800 MW) in its first phase and a total planned capacity of 4000 MW. It is the coal-based power plant of NTPC Limited. It is being built near Ramagundam in Peddapalli district.
The first unit, 800 MW, was inaugurated by Prime Minister Narendra Modi on 3 October 2023. The second unit was inaugurated by Modi on 4 March 2024.
Capacity The first unit of 800 MW was expected to be completed by the third quarter of 2020, but construction was halted due to COVID-19.
Unit Capacity (In MW) Date of Commissioning Status 1 800 05.09.2023 Commissioned 2 800 Under construction
References
External links
Executive Summary of Draft Zero date started for TSTPS