This is a list of power stations in Bangladesh. __TOC__

Nuclear Under construction NoPower stationLocationCapacity (MW)UnitsYearRefs1Rooppur Nuclear Power PlantRooppur24002 units 1200 MW VVER-1200/5232024

Coal fired

Power station Location Capacity (MW) Turbines Coal type Plant typeYear Refs Barapukuria Power StationDurgapur, Dinajpur 525 Anthracite Rampal Power StationRampal Upazila, Bagerhat District 1320 Sub-bituminousUltra super critical 2023Payra Power PlantKalapara Upazila, Patuakhali District 1320Sub-bituminousUltra super critical 2020Matarbari Power StationMaheshkhali Upazila, Cox's Bazar District 1200 Sub-bituminousUltra super critical2023

Oil and gas-fired thermal

Power station Location Capacity (MW) Refs Ashuganj Power StationBrahmanbaria 1627 Ghorasal Ghorasal 950 ShikalbahaShikalbaha, Chattagram 150 SiddhirganjSiddhirganj 260 Orion Group (4 plant)Narayangonj & Khulna400Lakdhanavi Bangla Power LimitedComilla52.2Desh Energy Chandpur Power Company Ltd.Chandpur200Doreen Power Generations and Systems Limited Group (3 plant)Nababganj, Manikganj & Munshiganj165Feni Lanka Power LimitedFeni114Manikganj Power Generations LimitedManikganj162Bhairab Power LimitedBhairab55Payra LNG Power PlantKalapara Upazila Patuakhali District3600 Gas turbines

Power station Max. capacity (MW) Turbines Fuel type Refs Meghnaghat 450 2+1 natural gas Ashuganj 146 2+1 natural gas Haripur 360 1+1 natural gas Goalpara, Khulna 265 heavy fuel oil (HFO) Mymensingh 210 4+1 natural gas Siddhirganj 240 natural gas

Gas engines

Power station Max. capacity (MW) Engines Fuel type Refs Baraka Power Ltd. 51 16 natural gas Dhaka 7 2 natural gas Gazipur 53 6 natural gas Gopalganj 100 16 natural gas Maona 35 4 natural gas Raozan 240 6 natural gas Ghorashal Regent 108 34 natural gas Baghabari, Sirajgonj 50 natural gasAPSCL, Ashuganj 50 natural gas

Hydroelectric

Power station Max. capacity (MW) Turbines Refs Karnafuli 230 5

Solar PV There are a number of utility-scale solar PV farms proposed in Bangladesh: 28 MW Teknaf Solar Park, 50 MW Sutiakhali, Mymensingh Solar Park and 32 MW Sunamganj Solar Park. US company SunEdison was the sponsor of the 200 MW Teknaf project while Singapore based entities Sinenergy Holdings, Ditrolic and local company IFDC Solar are the sponsors of the 50 MW Sutiakhali Solar Park. Edisun Power Point & Haor Bangla - Korea Green Energy Ltd is the 32 MW Sunamganj solar park project.

The government has taken a total of 19 solar power projects of total 1070 MW capacity which got the Prime Minister's approval in principle as part of its plan to generate 10 percent electricity from renewable energy source by 2020.

Of these, power purchase agreements (PPAs) were signed for only six projects of 532 MW, while nine projects of 483 MW await the PPA signing and four are in the process of project selection committee. Sun Solar Power Plant Ltd. installed a 5 MW solar power plant in Sylhet.

Combined cycle

Power station Location Capacity (MW) Refs Bheramara Combined Cycle Power PlantKushtia 410 Fenchugonj Combined Cycle Power PlantSylhet 180 Haripur 412 MW Combined Cycle Power PlantNarayanganj 412 Siddhirganj 335 MW Combined Cycle Power Plant (CCPP)Narayanganj 335Khulna 225 MW Combined Cycle Power PlantKhulna225

See also

Electricity sector in Bangladesh Energy policy of Bangladesh

References