The Flushing–Main Street station (signed as Main Street on entrances and pillars, and Main St–Flushing on overhead signs) is the eastern (railroad north) terminal on the IRT Flushing Line of the New York City Subway, located at Main Street and Roosevelt Avenue in Downtown Flushing, Queens. It is served by the 7 local train at all times and the <7> express train during rush hours in the peak direction.
The Flushing–Main Street station was originally built as part of the Dual Contracts between the Interborough Rapid Transit Company (IRT) and the Brooklyn–Manhattan Transit Corporation (BMT). It opened on January 21, 1928, completing the segment of the Flushing Line in Queens. Although plans existed for the line to be extended east of the station, such an extension was never built. The station was renovated in the 1990s. The Metropolitan Transportation Authority (MTA) began constructing additional staircases, including four new entrances, at the station in 2022.
The station has two island platforms and three tracks; the platforms are connected at their eastern end. There are nine entrances at street level, leading to two separate fare control areas at Main Street and at Lippmann Plaza. There is an elevator, which makes the station compliant with the Americans with Disabilities Act of 1990. The station is listed on the National Register of Historic Places. In 2024, it was the second-busiest station outside of Manhattan, as well as the 10th busiest subway station in the system.
History Planning and construction
The 1913 Dual Contracts called for the Interborough Rapid Transit Company (IRT) and Brooklyn Rapid Transit Company (BRT; later Brooklyn–Manhattan Transit Corporation, or BMT) to build new lines in Brooklyn, Queens, and the Bronx. Queens did not receive many new IRT and BRT lines compared to Brooklyn and the Bronx, since the city's Public Service Commission (PSC) wanted to alleviate subway crowding in the other two boroughs first before building in Queens, which was relatively undeveloped. The IRT Flushing Line was to be one of two Dual Contracts lines in the borough, and it would connect Flushing and Long Island City, two of Queens's oldest settlements, to Manhattan via the Steinway Tunnel. When the majority of line was built in the early 1910s, most of the route went through undeveloped land, and Roosevelt Avenue had not been constructed. Community leaders advocated for more Dual Contracts lines to be built in Queens to allow development there.
At the time of the line's planning, Downtown Flushing was a quiet Dutch-colonial-style village; what is now Roosevelt Avenue in the area was known as Amity Street, a major commercial thoroughfare in the neighborhood. In late 1912, Flushing community groups were petitioning the Public Service Commission (PSC) to depress the proposed line in Flushing into a subway tunnel, rather than an elevated line. Unlike a subway, an el would cause disturbances to the quality of life and a loss in nearby property values, as well as a widening of Amity Street that would cause more changes to the already existing town. One Amity Street property owner compared the planned effect of an elevated Flushing Line on Amity Street to the degradation of Myrtle Avenue in Brooklyn after the Myrtle Avenue Elevated was built there. On the other hand, a subway would only require that the street be widened, even though it was more expensive than an elevated of the same length.
On January 20, 1913, because of these concerns, the Flushing Association voted to demand that any IRT station in Flushing be built underground. Due to advocacy for elevated extensions to the line past Flushing (see ), the PSC vacillated on whether to build a subway or elevated for the next few months. The PSC finally voted to bring the Flushing portion of the line underground in April 1913. However, as the costs of a subway had increased by then, they decided to postpone discussion of the matter. In June 1913, the New York City Board of Estimate voted to allow the line to be extended from 103rd Street–Corona Plaza east to Flushing as a three-track line, with a possible two-track second phase to Bayside.
The Flushing Line west of 103rd Street opened in 1917. The IRT agreed to operate the line under the condition that any loss of profits would be repaid by the city. As part of the agreement, the PSC would build the line eastward to at least Flushing. The station, as well as two other stations at Willets Point Boulevard and 111th Street, was approved in 1921 as part of an extension of the Flushing Line past 103rd Street. Construction of the station and the double-deck bridge over the Flushing Creek began on April 21, 1923, with the station built via cut-and-cover methods. The bridge was completed in 1927, and the station opened on January 21, 1928, over a decade after the line initially began operation.
Proposed extension of the line
The station was not intended to be the Flushing Line's terminus. While the controversy over an elevated line in Flushing was ongoing in January 1913, the Whitestone Improvement Association pushed for an elevated to Whitestone, College Point, and Bayside. However, some members of that group wanted to oppose the Flushing line's construction if there was not going to be an extension to Whitestone. After the January 20 vote to demand that the subway line through Flushing be built underground, groups representing communities in south Flushing collaborated to push for an elevated along what was then the LIRR's Central Branch, in the current right-of-way of Kissena Corridor Park. Eleven days later, the PSC announced its intent to extend the line as an el from Corona to Flushing, with a possible further extension to Little Neck Bay in Bayside. There was consensus that the line should not abruptly end in Corona, but even with the extension to Bayside, the borough would still have fewer Dual Contracts route mileage than either Brooklyn or the Bronx. The New York Times wrote that compared to the Bronx, Queens would have far less subway mileage per capita even with the Flushing extension.
The Bayside extension was tentatively approved in June 1913, but only after the construction of the initial extension to Flushing. Under the revised subway expansion plan put forth in December 1913, the Flushing Line would be extended past Main Street, along and/or parallel to the right-of-way of the nearby Port Washington Branch of the LIRR towards Bell Boulevard in Bayside. A spur line would branch off north along 149th Street towards College Point.
In 1914, the PSC chairman and the commissioner committed to building the line toward Bayside. However, at the time, the LIRR and IRT were administered separately, and the IRT plan would require rebuilding a section of the Port Washington branch between the Broadway and Auburndale stations. The LIRR moved to block the IRT extension past Flushing since it would compete with the Port Washington Branch service in Bayside. One member of the United Civic Association submitted a proposal to the LIRR to let the IRT use the Port Washington Branch to serve Flushing and Bayside, using a connection between the two lines in Corona. The PSC supported the connection as an interim measure, and on March 11, 1915, it voted to let the Bayside connection be built. Subsequently, engineers surveying the planned intersection of the LIRR and IRT lines found that the IRT land would not actually overlap with any LIRR land. The LIRR president at the time, Ralph Peters, offered to lease the Port Washington and Whitestone Branches to the IRT for rapid transit use for $250,000 annually (), excluding other maintenance costs. The lease would last for ten years, with an option to extend the lease by ten more years. The PSC favored the idea of the IRT being a lessee along these lines, but did not know where to put the Corona connection. Even the majority of groups in eastern Queens supported the lease plan. The only group who opposed the lease agreement was the Flushing Association, who preferred the original Flushing subway plan.
Afterward, the PSC largely ignored the lease plan since it was still focused on building the first phase of the Dual Contracts. The Flushing Business Men's Association kept advocating for the Amity Street subway, causing a schism between them and the rest of the groups that supported the LIRR lease. Through the summer of 1915, the PSC and the LIRR negotiated the planned lease to $125,000 a first year, , with an eight percent increase each year; the negotiations then stalled in 1916. The Whitestone Improvement Association, impatient with the pace of negotiations, approved of the subway under Amity Street even though it would not serve them directly. The PSC's chief engineer wrote in a report that a combined 20,600 riders would use the Whitestone and Bayside lines each day in either direction, and that by 1927, there would be 34,000 riders per day per direction. The Third Ward Rapid Transit Association wrote a report showing how much they had petitioned for Flushing subway extensions to that point, compared to how little progress they had made in doing so. Negotiations continued to be stalled in 1917. Despite the line not having been extended past Corona yet, the idea of a subway extension to Little Neck encouraged development there.
The Whitestone Branch would have had to be rebuilt if it were leased to the subway, with railroad crossings removed and the single track doubled. The PSC located 14 places where crossings needed to be eliminated. However, by early 1917, there was barely enough money to build the subway to Flushing, let alone a link to Whitestone and Bayside. A lease agreement was announced on October 16, 1917, but the IRT withdrew from the agreement a month later, citing that it was inappropriate to enter such an agreement at that time. Thereafter, the PSC instead turned its attention back to the Main Street subway extension.
Even after the station opened in 1928, efforts to extend the line past Flushing persisted. In 1928, the New York City Board of Transportation (BOT) proposed allowing IRT trains to build a connection to use the Whitestone branch, but the IRT did not accept the offer since this would entail upgrading railroad crossings and the single-tracked line. Subsequently, the LIRR abandoned the branch in 1932. As part of the 1929 IND Second System plan, the Flushing Line would have had branches to College Point and Bayside east of Main Street.Board of Transportation of the City of New York Engineering Department, Proposed Additional Rapid Transit Lines And Proposed Vehicular Tunnel, dated August 23, 1929 That plan was revived in 1939.Project for Expanded Rapid Transit Facilities, New York City Transit System, dated July 5, 1939 The BOT kept proposing an extension of the Flushing Line past Main Street until 1945, when World War II ended and new budgets did not allow for a Flushing extension. In 1956, the Queens Chamber of Commerce and Queens Transit Committee again proposed the extensions east of the station to Bayside and College Point, along with a new spur along Kissena Boulevard running south to Sutphin Boulevard in Jamaica and eventually leading to John F. Kennedy International Airport. Since then, several New York City Transit Authority proposals for an eastward extension have all failed.
Later years 1930s to 1960s