The Broadway Tunnel was a tunnel under Fort Moore Hill in Downtown Los Angeles, California. It extended North Broadway (formerly Fort Street), at Sand Street (later California Street), one block north of Temple Street, northeast to the intersection of Bellevue Avenue (later Sunset Boulevard, now Cesar Chavez Avenue), to Buena Vista Street (now North Broadway).
History A proposal for opening Broadway through to Buena Vista Street and extending the street south into what was then part of Main Street, below Tenth Street — to give a continuous, wide thoroughfare from the southern city limits to the Eastside — was made as early as February 1891."Sou', Sou'west." Los Angeles Times. Feb. 26, 1891. p. 4.
Plans were prepared by the city engineer's office in early March 1895."The Broadway Tunnel; Plans Prepared By The City Engineer." Los Angeles Times. Mar. 3, 1895. p. 13. The main argument for its construction was that a tunnel providing an additional opening on the north would lessen the constantly increasing traffic (horses, buggies and wagons), which was causing a dangerous jam at the corner of First and Spring Streets."The Broadway Tunnel." Los Angeles Times. May 12, 1896. p. 6.
Construction Work began on the Broadway Tunnel on November 2, 1899. About 25 men with teams (of animals) moved obstructions out of the way in preparation for the excavation,"Tunnel Work Commenced; Begin To Dig." Los Angeles Times. Nov. 3, 1899. p. 10. from the north approach."City Tunnel Work; Figures And Statistics; Broadway Tunnel." Los Angeles Times. Dec. 15, 1899. p. A 1. On the morning of January 20, 1900, a laborer was buried under about 20 tons of earth at the north end of the tunnel. The wood bracing fell over the man in such a manner that he was saved from being crushed to death."Broadway Tunnel Accident." Los Angeles Times. Jan. 20, 1900. p. 15.
The tunnel required more than 50,000 cubic yards (38 227.75 m3) of elevation, 4,000 cubic yards (3 058.22 m3) of concrete and 1.25 million of bricks to line it. With the exception of the tunnel in Fairmount Park in Philadelphia, which was in diameter, but only long, the Broadway Tunnel was the widest tunnel of its type in the U.S., and possibly in the world, at that time."Field Work Done By City Engineer; Broadway Tunnel Creditable." Los Angeles Times. Dec. 23, 1900. p. I 8. According to an article in the Los Angeles Times, the Third Street Tunnel, which was also nearing completion at the time, could have been put inside the Broadway Tunnel leaving enough room for a sidewalk wide.
The Broadway Tunnel was completed and opened for traffic on Saturday, August 17, 1901. It was long, wide and high, with a grade of 6 in 100, falling toward the east."City Tunnels." Los Angeles Times. Feb. 3, 1901. p. C 2. The cost in its construction was $66,000."Tunnel Completed." Los Angeles Times. Aug. 14, 1901. p. 10
Reconstruction The Broadway Tunnel was closed for reconstruction in 1915. The roadway was lowered to decrease the grade, wood block flooring was installed to provide a noiseless surface for the traffic of teams and automobiles, and a false roof built inside the original shell. Because of the lowering, it was necessary to make a cut of in California Street, and to change the grade of North Broadway from Temple Street to the tunnel. The concrete archway of the Broadway Tunnel was high, and the entire bore was lined with white glazed tile. The stairway on the outer face of the southern portal was extended to a rise of to Fort Moore Hill."Great Artery Is Completed; Broadway Tunnel to be Turned Over to City Saturday; Notable Celebration by Civic Organizations Planned; Reconstruction Bore One of the Finest in Country." Los Angeles Times. Feb. 17, 1916. p. II 1.
The work was completed and the Broadway Tunnel reopened in early February 1916. Due to the importance of the artery of travel, through which thousands of automobiles, teams and pedestrians would be passing daily, an event was held on Saturday, February 19, formally turning the tunnel over to the city, with the Automobile Club of Southern California in charge.
Closure The Broadway Tunnel was closed on June 2, 1949."Broadway Tunnel Closed Last Night." Los Angeles Times. Jun. 3, 1949. p. A 1. It was demolished for the construction of the new Hollywood Freeway (U.S. Route 101) through Downtown."Old Broadway Tunnel Goes Out With Roar." Los Angeles Times. Sep. 22, 1949. p. 2. The route cut through Fort Moore Hill and made it necessary for a Broadway overpass to be built across the freeway at the former Broadway Tunnel site.